May 07, 2005

Today the crew focused on plumbing and electrical. When M arrived this morning, we went over

We also asked the crew to move the window.

M explained that the plywood they put up yesterday was merely to appease the inspector (?). They planned to take it down before installing a vapor barrier and insulation.


They moved the window. Now it's 2" too high. I guess we'll live with that. As promised, the plywood is down and the vapor barrier is up.


They installed a bunch of outlets and wall switches.


Wiring for the wall sconces.


Plumbing for the sink and toilet