Today the crew did more framing: they finished the left doorway, framed the internal wall between the bathroom and closet, and reframed the right doorway to its correct position.
|
|
|
|
Now that the internal wall is up, it's easier to see how the space will be partitioned.
|
|
|
|
Details of the left (bathroom) door:
Our double-hung windows arrived.
I stuck the camera into the former heating vent hole and took a picture of the sewage line below the floor. Is the section of pipe in the lower center actually connected to something?